Construction is near the halfway point for the three-level parking structure in
Lot No. 5. The first deck is nearly completed, all columns have been installed
and underground utilities are in place. Groundbreaking was held on June 18, 2008,
and completion is projected for July 2009.
With enough room for 1,431 vehicles, the parking structure also will include
an adjacent 3,200-square-foot facility for new Public Safety offices. McCarthy
Building Cos. Inc. is the general contractor with Ken Emmons of Gafcon as
project manager and International Parking Design as the project architect.
Sections of metal trellises with stucco and brick veneer will attach to
the external facade. Two pedestrian bridges will connect the main
campus to the parking structure. Once completed, parking on
campus will be maximized.
The parking expansion is part of a facilities master plan designed to
accommodate 20,000 students. The parking structure is one of several
capital improvement projects made possible by the Grossmont-Cuyamaca
Community College District’s $207 million Proposition “R” bond measure
approved by East County voters in 2002.